§ 15.5-56. Engineering.  


Latest version.
  • (a)

    The developer shall retain a professional engineer, licensed to practice in the State of Florida, to supervise and control all work done, including all location and control staking, clearing, grading, stabilizing, placing of bases, surfacing and drainage. The developer shall have available, when necessary, qualified personnel for the purpose of setting all line and grade stakes and for verification of points by the county engineer.

    (b)

    Each stage of road construction (such as clearing, grading, stabilization, base, surface and drainage facilities) and any other item as deemed appropriate by the county engineer, shall receive specific inspection and approval from the developer's engineer with appropriate records to verify all such inspections and approval. All field notes must be made available to the county engineer at any time prior to acceptance.

    (c)

    It will be the responsibility of the developer or his professional engineer to authorize or to make the following tests during the construction period and furnish the county engineer with a copy of each test made:

    (1)

    Surface course material and density.

    (2)

    Base material and density.

    (3)

    Subgrade bearing value.

    (4)

    Subgrade density.

    (5)

    Stabilized roadway bearing value.

    (6)

    Stabilized roadway density.

    (7)

    Stabilized roadway thickness.

    (8)

    Concrete strength, twenty-eight (28) days.

    (9)

    Embankment density.

(Ord. No. 89-7, § 5.7, 5-16-89)